This kit requires some materials that are not included in the kit. Hey we've done all the heavy lifting here. Most robot builders have these sort of things on their work bench.
- 28 gage hook up wire. Two colors aprox. 26" long per leg.
Wire, connectors, and Crimper
Extra wire and connectors - Short (5/8") pieces of 3/8" heat shrink.
Local hardware store. - Super Glue or Lock Tite.
Local hardware store. - Some method of adding connectors to the wires.
With the wire and crimper above.
Step 1Attachment:
afsa01.jpg [ 36.32 KiB | Viewed 3005 times ]
First we need to install the rubber end cap onto the aluminum hub part. I haven't glued them in place. Not sure if it's necessary yet.
Step 2Attachment:
afsa02.jpg [ 35.61 KiB | Viewed 3005 times ]
Find a good quality scissors for this step. Begin by cutting down the extra from the end cap.
Step 3Attachment:
afsa03.jpg [ 40.45 KiB | Viewed 3005 times ]
Continue in a spiral till you get to the hub. Push the end cap on again to make sure it's still tight and cut as closely as you can.
Step 4Attachment:
afsa04.jpg [ 30.81 KiB | Viewed 3005 times ]
It should look something like this. If it extends beyond the edge it might take too much pressure to make the switch close.
Step 5Attachment:
afsa05.jpg [ 44.72 KiB | Viewed 3005 times ]
Insert one of the nylon shoulder washers into the hub.
Step 6Attachment:
afsa06.jpg [ 48.54 KiB | Viewed 3005 times ]
Install the spring and the other nylon shoulder washer into the hub.
Step 7Attachment:
afsa07.jpg [ 42.1 KiB | Viewed 2998 times ]
Bring it all together.
Step 8Attachment:
afsa08.jpg [ 23.7 KiB | Viewed 3005 times ]
Add one nut. Tighten it down all the way. Then back it off one half revolution. There are 40 threads per inch. By backing it off one half turn the throw of the switch assembly is about 12 thousandths of an inch.
Step 9Attachment:
afsa09.jpg [ 52.88 KiB | Viewed 3005 times ]
Cut a section of 28 gage wire to about 26" long. Strip off about 7/8" of insulation from one of the ends.
Step 10Attachment:
afsa10.jpg [ 68.29 KiB | Viewed 3005 times ]
Wrap it around the end of the stud and twist it tight. This is tight, but it has to be in order to fit inside the short 1.5" tube.
Step 11Attachment:
afsa11.jpg [ 61.14 KiB | Viewed 3005 times ]
Add another nut, and tighten it down. Again I know it's tight. But can be done with some care. It would be a good idea to add a little super glue to the nuts to keep them in place.
Attachment:
afsa16.jpg [ 38.08 KiB | Viewed 2956 times ]
Step 12Attachment:
afsa12.jpg [ 62 KiB | Viewed 3005 times ]
Add some heat shrink to keep the wire from twisting.
Step 13Attachment:
afsa13.jpg [ 53.99 KiB | Viewed 2956 times ]
Cut a section of 28 gage wire to about 26" long. Strip off about 1/2" of insulation from one of the ends. Use a different color for this one.
Step 14Attachment:
afsa14.jpg [ 24.82 KiB | Viewed 2956 times ]
Feed the bare end of the wire into an unused mounting hole for the ASB-06 or whatever you are attaching the HUB-08 to. Make sure the insulation doesn't go in too far.
Step 15Attachment:
afsa15.jpg [ 24.22 KiB | Viewed 2956 times ]
Attach the HUB-08 to the ASB-06.
Step 16Attachment:
afsa16.jpg [ 38.08 KiB | Viewed 2956 times ]
Attach the tube and the switch assembly a shown. That completes the assembly guide.
Note: need wiring example for pull up resistor to an I/O pin.